 CSA / Zone Update 06-26-2017

 

BOLT Active Service Area:

 

Additional contractor and engineering firm have been brought in to expedite drop installation in areas where services have already been established. 

Current lead time is 6-8 weeks.  More crews are being brought in to decrease this time as expediently as possible.

***NOTE*** Customers on Empire Electric or PSO may experience delays in receiving service in Hot Shot areas of up to 6 months.

 

ADAIR TOWN:

ADAR

Active Service in Adair town.

AFTON TOWN:

AFTN, AFTS

Active service in Afton town.

GROVE RURAL/TOWN:

HNCK, BUFF, MAIN, MANO, PTIS, PTES, TLND, BYCT, PKPL, GRSW, GOVR

 Active service in Buffalo Shores, North and South, Governors Retreat Area, as well as Patricia Island.

GROVE/WYANDOTTE/TURKEY FORD RURAL:

ICEB, TURK, TKFD

Home installs have begun and drop placement will continue until all customers have received service.

KETCHUM/LANGLEY/CLEORA RURAL:

Active service east of Cleora, south of Ketchum, as well as north of Langley.

MIAMI/QUAPAW/PEORIA RURAL:

NERV, MIST, SPRV, SRES

The Hot Shot customers continue to be placed daily.  There are multiple line extensions that need completed in this process.  All customers signing up should see service in 30 days or less.

MONKEY ISLAND/AFTON RURAL:

Active service area in nearly all of Monkey Island, with a few exceptions.  Active service east of Bernice to Copeland area.

VINITA RURAL:

VNHS, PYRD, WOAK, SWCT, VOLT, VSOT, 

Active service north and east of town.

ZENA RURAL:

ZP00, ZP01, ZP02, ZP03

Active service north and west of Zena.

 

BOLT Construction Area:

 

 MIAMI/QUAPAW/PEORIA:

MIAM, PEOR, NORE

All mainline construction will be complete by 6/17 along with the majority of the drops. The remaining drops are scheduled for completion by mid-July. 

BERNICE TOWN:

BTNO/BTSO

Construction started March 20 and will last approximately 120 days.

CHELSEA TOWN:

CTNO, CTSE, CTES, CTEN

Mainline construction is complete and home installation will be starting 6/20.  Drop installation will continue until all drops are placed.

CHELSEA/ADAIR RURAL:

CHEL, CHSW, CTST, ADWE, CHTW

Mainline construction and the majority of the drops will be complete by the end of June with home installs starting early July.  Drop installation will continue until all customers have received service.

COLCORD/WEST SILOAM SPRINGS AREAS:

COLC, COLW, CORE, DRIP, GRCY, SILN, SILO, SIRN, SIRW

Construction started in mid-March and should be completed late July.  Drops and inside installations will follow.

GROVE TOWN:

BDWY, GATE, GROV, HOUS, LOWE, LSRD, MADS, NOTS, PARK, STPK, TURT

Construction started March 20 and will last approximately 120 days.

GROVE/FAIRLAND RURAL:

BLUE, CAYU, CHEE, CHQN, FREA, LOST, MKNE, MKNR, PARK, POLE, REED,  SAIL, WALN, WOLF, WOOD

Construction has started and should become live mid-summer.

KETCHUM TOWN: (PSO Areas)

Construction started March 20 and last approximately 120 days.

LANGLEY TOWN: (PSO Areas)

Construction started March 20 and last approximately 120 days.

 

BOLT Future Buildouts:

 

Areas not currently deployed or under construction are now on indefinite hold.  Due to various obstacles, a fast approaching loan deadline, and other factors affecting market entry, BOLT has been forced to take a demand based approach.  As construction plans change and develop, new information will be made available.

 

 

EXCEPTIONS:

Monkey Island Area:

Mainstay – Will not grant easement

White Chapel – Will not grant easement

Sheuline Estates – Will not grant easement