 CSA / Zone Update 3-10-2017

 

BOLT Current Service Area:

 

Hot Shot drops (drops in areas where service is already established) are moving much more efficiently.  All sign ups since Thanksgiving have been seeing service within 4-6 weeks, many even quicker.  We continue to look for ways to decrease the wait time.  BOLT has enhanced in house crew capabilities and has brought in a second engineering firm and construction contractor dedicated solely to this area of construction. 

MIAMI/QUAPAW/PEORIA:

NERV, MIST, SPRV, SRES

The Hot Shot customers continue to be placed daily.  There are multiple line extensions that need completed in this process.  All customers signing up should see service in 30 days or less.

MIAMI, PEOR, NORE

Construction on the remaining work has begun and is anticipated to last 60 days throughout all areas.  As routes and drops are completed, they will be installed.

ADAIR TOWN:

ADAR

Services have been established in Adair.  Drops continue to be placed and will be turned on as quickly as possible.

AFTON TOWN:

AFTN, AFTS

Services have been established in Afton.  Drops continue to be placed and will be turned on as quickly as possible.

 

 

BOLT Current/Near Construction Area:

 

BERNICE TOWN:

BTNO, BTSO

Construction will start March 20 and last approximately 120 days.

CHELSEA TOWN:

CTNO, CTSE, CTES, CTEN

Construction has started and will last approximately 90 days.  Drop placement will begin shortly.  We anticipate service to all pre-pays in mid-April.

CHELSEA/ADAIR RURAL:

CHEL

Drop placement will begin shortly.  We anticipate service to all pre-pays in mid-April.

CHSW, CTST, ADWE

Drop placement will begin shortly.  We anticipate service to all pre-pays in late-April.

COLCORD/WEST SILOAM SPRINGS AREAS:

COLW, COLC, CORE, GRCY, DRIP, SIRW, SILO, SIRN, SILN

Construction has started and will last approximately 90 days.

DRY GULCH/PRYOR/MAZIE:

GULC, BELL, DRYG, PRNE, HOME, HMNO, HMSO

Final RUS approval has been received.  Construction will start in March and last approximately 120 days.

GROVE/WYANDOTTE/TURKEY FORD:

ICEB, TURK, TKFD

Construction started in mid-December and is expected to be completed by late March.

GROVE:

SAIL, CHQN, NOTS, TURT, CHEE, GROV, HOUS, PARK, BDWY, LSRD, GATE, STPK, LOWE

Construction will start March 20 and last approximately 120 days.

GRSW

Construction started in February and will last approximately 60 days.

 KETCHUM TOWN: (PSO Areas)

KETS

Construction will start March 20 and last approximately 120 days.

LANGLEY TOWN: (PSO Areas)

LANG

Construction will start March 20 and last approximately 120 days.

VINITA RURAL:

VNHS, WOAK, PYRD, SWCT

VNHS – Anticipate completion by end of March.

WOAK - Anticipate completion first of April.

PYRD - Anticipate completion early April.

SWCT - Anticipate completion by end of April.

 

 

BOLT Future Buildouts:

 

AFTON/BERNICE/CLEORA RURAL:

AFRE, BNRL, HORS, CLEO

Tentative completion date early 3rd quarter 2017

CHELSEA/ADAIR RURAL:

CHNO, CHNC, BUSH, CHLW

Tentative completion early 3rd quarter of 2017.

CHOUTEAU RURAL:

POAK, QUIN

These CSA’s have been staked and submitted to PSO for pole attachment approval.  Timing is dependent on PSO approval but is anticipated to be complete early third quarter 2017.

CHOUTEAU TOWN:

CHTW, HILL, CHOW, CHTE

These CSA’s have been staked and submitted to PSO for pole attachment approval.  Timing is dependent on PSO approval but is anticipated to be complete early third quarter 2017.

 DRY GULCH/PRYOR/MAZIE RURAL:

HMSE, OSES, PRSW, ACRE, BNGE, MIDA, NETC

These CSA’s have been staked and submitted to PSO for pole attachment approval.  Timing is dependent on PSO approval but is anticipated to be complete early third quarter 2017.

FAIRLAND RURAL:

WNUT, HICK, HKMD, LKPT, POLE, SERV

On hold pending resolution of issues with incumbent telco provider and NEOEC.  Tentative completion late 2nd quarter of 2017.

FAIR, FASE, FRNE

Tentative completion date early 3rd quarter 2017.

FREA, FLTS, MKNE, MKNR

An amendment to an existing contract is being developed to get construction started in these areas.  This process takes time with RUS be we anticipate construction to begin around April.

FAIRLAND TOWN:

FLTN, FLTW

The City of Fairland project has been place on indefinite hold after delays in obtaining a franchise agreement from the City of Fairland.

BOLT is developing an amendment to move construction into the rural areas surrounding Fairland as quickly as possible.

GROVE:

MADS, GRSE, DODG, YUGA, LOST, WALN, BLUE, WOLF, WOOD, CAYU, REED

The CSA’s listed above are currently staked.  Most of these require PSO pole attachment permits to be submitted which is complete.  Right now we are looking at an approximate start date for construction in February-March with construction lasting approximately 120 days.  This timeframe may be extended should PSO permitting take longer than estimated.  We have a tentative completion date of 3rd quarter of 2017.

MIAMI RURAL:

WERN, MINO, WDTY, NARC, DOTY

We have a tentative completion date of 3rd quarter of 2017.

Newport Village on Monkey Island:

Construction has been postponed in this subdivision until the take rate is at minimum 50%.

Stoneridge Lane/Granite Drive/Grand Point in Ketchum:

Construction began the week of November 21 and will be completed by late-April.

 

EXCEPTIONS:

ADRE, ADRS, TWIN, PENS, CHNE

These CSA’s will be built in late 2017 pending available funds remaining in the project scope.

Monkey Island Area:

Mainstay – Will not grant easement

White Chapel – Will not grant easement

Sheuline Estates – Will not grant easement